September 24, 2013 > South Grimmer road closures scheduled

South Grimmer road closures scheduled

Submitted By City of Fremont

As part of the BART Warm Springs Extension Project, full road closures are planned on South Grimmer Boulevard between Old Warm Springs/Lopes Court and Osgood/Warm Springs Boulevard on the following dates:

Saturday, September 28: 7 a.m. to 7 p.m., to pour West Bridge Deck
Saturday, October 5: 7 a.m. to 7 p.m., to pour East Bridge Deck
Saturday, October 12: 7 a.m. to 7 p.m., to remove Falsework & Brackets

There will be a short detour around the area to Auto Mall Parkway. The contractor expects to complete their work at the Grimmer underpass by the end of October.

Home        Protective Services Classifieds   Community Resources   Archived Issues  
About Us   Advertising   Comments   Subscribe   TCV Store   Contact

Tri Cities Voice What's Happening - click to return to home page

Copyright © 2014 Tri-City Voice