Approved plans and specifications for utilities SCADA software conversion and programming update project. A supervisory control and data acquisition (SCADA) system monitors, gathers data and controls water distribution and collection and treatment of wastewater. Open bids on Oct 20, award contract on Nov 3. Estimated project costs: $1,025,700. To be completed by June 2010. Funding sources: sewer and water funds.
City Manager to negotiate and enter into a contract with Deltawrx for project management services for the proposed Public Safety Computer Aided Dispatch/Records Management System (CAD/RMS).